DEVELOPMENT – TRACKWORK (STEP 1.2.1) – Page 7

 

Page 1

 

Page 2

 

Page 3

 

Page 4

 

Page 5

 

Page 6

 

Page 7

 

Main development page

 

HOME

 

 

 

The final furlong (uploaded 24 May 2010)

With the trackwork passed for running by HM Railway Inspector it is likely that this will be the final page on trackwork.  Our previous page noted that we had reached the end of the line, but there were still some jobs outstanding.  We listed:

 

(a)   removal of some largish tree roots from the trackbed by machine which were too large to move by means of pick, shovel, crowbar and profane language

(b)   clearance of ditches (including work associated with clearing November’s landslip

(c)   installation of bufferstops and a sand drag south of Blaenavon (High Level) station    @

(d)   installation of a properly engineered foot crossing near Forgeside, now called ‘Glantorfaen Crossing’

(e)   installation of a properly engineered foot crossing immediately south of Blaenavon (High Level) station    @

(f)   installation of facing point locks on all the points noted above    @

 

Although all the items noted above are complete, nothing has yet been said of items marked ‘@’.  This page seeks to put matters right.

 

Additionally two more jobs have been awarded to contractors, as noted below:

(a)   Tamping and Lining (by contractors Railway Support Services)

(b)   Ballast Brushing (again, by Railway Support Services)

 

Bufferstops,  sand drag and foot crossing at Blaenavon (High Level).

It has been calculated that the maximum speed that a vehicle could attain whilst running from Whistle in to Baenavon (High Level) woud be a fraction over 74mph.  We stress that this is a theoretical value, and that because the gradient eases as the station is approached, and level through the station itself, not to mention the stiff bearings on our elderly stock, we’d be lucky to get a real terminal velocity of 20mph.  All the same, 200 tons of train reaching the end of the line, even at 20mph would make quite a mess.  For that reason we have not only a bufferstop, but a sand drag, which , like an escape lane on a mountain road, would provide sufficient friction to stop or at least substantially slow any runaways.

 

Well it’s finished now, and hopefully it will disappear when we make a short extension over the bridge in the next two or three years.  Hopefully we won’t have need of its services

 

The buffer stop is in place and just waits for the bufferbeam itself to be fitted.  Ballast extends all the way to the finish.

1054 - 28 Mar 10

The baulks that will contain the sand for the sand drag are fitted byPBR volunteers.

 

1082 – 4 April 2009

 

Here’s a longer view of the situation.  There remains a substantial clearing up job to do on the righf.  The apparent pile of rubble on the left is the wall of the erstwhile LNWR water crane.  Most of the damage has occurred in the last three years.  There are plans to restore it in due course...

1085 – 4 Apr 10

The baulks are now fitted, and viewed from the other side of the line, the full extent can be seen

 

 

1116 – 10 April 10

 

The filling of the sand drag with the regulation soft sand was an irksome task with plant barely suited to the job….

 

1224 – 9 May 10

…and an ill-disciplined semi-permeable membrane seemed determined to make things even more irksome by blowing about in even the faintest breeze, .  Bricks are borrowed from the damaged water tower in order to weight the membrane down.

1225 – 9 Mayl 10

 

Backs are strained as sand is spread into the space allocated.  Even HM Railway Inspector was surprised to see just how much sand was involved.

 

 

1228 – 9 May  10

The finished sand drag.  It has been installed in order to prevent any train which over runs the station from hitting the buffers too sharply, and works in exactly the same way as the ‘escape lane’ seen close to the bottom of some of the more notorious local road inclines.  We very much hope that it will never be used!

1237 – 15 May 10

 

 

Ballasted track at  Forgeside

Here are some views from Bridge 18 (Forgeside  Road), south and north respectively…

 

Stretching south,we get some impression of the huge amount of  work done.  In the middle-far distance lies the newly constructed Glantorfaen Crossing, the track then does a gentle curve to the right and it may just be possible to see the building at Blaenavon (High Level) station.  Another large stump awaits removal in the right foreground – it’s days are numbered!

1164 – 24 Apr 10

Looking north we see the area once occupied by the so-called Tyre Mill Sidings.  The sidings were in the area to the left.  The low wall between the cycle way and the track is a remnant of those days.  The curious joggle in the distance is a consequence of some slueing undertaken some time after 1960 for reasons which are largely unexplained.

1165 – 24 April 10

 

 

In these last few frenetic days before we open for public service over the extension It seemed an opportune moment to do a bit of ‘before and after’ comparison.  Although, in terms of the season, they were taken six months apart.  This picture, reproduced from Page 1, and taken by member Andy Knock,  and was taken in September 2007.  Notwithstanding the change in season, and the slight difference in viewpoint  the difference is astonishing, and the amount of physical work difficult to comprehend.  There is no doubt that the appearance of the track in the upper image is a bit raw, and there are still some earthworks and landscaping work to do, but nature will certainly smooth some of the rough edges.  It will be interesting to take another picture in September 2010 .

 

And that is almost the end of the tracklaying in Step1.2 story except that we are awaiting images from the final tamping and ballast brushing exercise and of the fitting of facing point locks.  As soon as they arrive we’ll make the final upload on this page.  

 

 

 

Page 1

 

Page 2

 

Page 3

 

Page 4

 

Page 5

 

Page 6

 

Page 7

 

Main development page

 

HOME