DEVELOPMENT – TRACKWORK (STEP 1.2.1) – Page 6

 

Page 1

 

Page 2

 

Page 3

 

Page 4

 

Page 5

 

Page 6

 

Page 7

 

Main development page

 

HOME

 

 

 

Trackwork through Blaenavon (High Level) station – and the end of the line (uploaded 18 May 2010)

We have been somewhat remiss in reporting on trackwork matters, and it has been over five months since our last update.  Many things have happened, and there has been a major shift in the emphasis on the track as the work approaches completion.  Perhaps the single greatest hindrance to progress was the heavy and persistent snow which covered the track, often to a depth of several feet, and which had made work quite impossible.  The snow, together with significant and lengthy interruptions in our funding, made a substantial re-think in strategy a priority, and contractors were brought in to assist during the final stages, in order to regain time.  We had always planned this, but the extent to which they were employed was rather greater than first envisaged.  This gave us rapid progress, (though at disproportionate cost) but not enough of it.  It was delay in bringing the track up to standard that was the main feature, at the time of writing, in causing a two month delay to our opening date.

 

If that pre-amble sounds a trifle gloomy, on the ground, the visual differences are now clear to see, and impressive by any standards. The first success was the completion of the apparently endless task of replacing the rotten sleepers. There was a time when we thought that we’d only need to change some of them, but in the end, the gold-plated solution was adopted, and we changed all of those sleepers that were not already concrete.  Completion was reported on Page 5, and, for the record, the last sleeper was changed on 15 November 2009.  Work had begun in June 2008.

 

During the final months of 2009 a technical problem with the rail threatened to seriously impede progress.  For many years the line had been used to carry coal, and was classified as a ‘mineral line’.  This permitted relaxed standards to apply to track laying.  In particular when it is necessary to cut a 60ft length of rail to something shorter, it was permissible to burn off the rail end using oxy-acetylene.  However, since the Hither Green rail accident in November 1967 when 49 people were killed as the result of a broken rail end, the use of oxy-acetylene for cutting has been absolutely forbidden on passenger lines.  Rail-ends must now be sawn with saws, or cut with cutting discs.  Although we knew there were a few ‘burnt’ rail ends, as the sleeper replacement work approached completion it was clear that the total would be large, and no less than 43 rails had burnt ends.  Fortunately an excess of rails had been ordered for the Big Pit branch when steel prices were low, so the financial impact was not perhaps what it might have been.  Nonetheless during October, November and December some forty 60ft length of rail were taken down and dumped alongside the track.

 

In late December the first contract was let to contractors KG Price of Cardiff to replace burnt rails, and the adjust the rails to form correctly positioned and gapped rail ends.  It had been planned to let this contract somewhat earlier, but delays in securing funding frustrated our plans.  Bad weather ensured this work didn’t start for another month.  In early January a second contract was let to the same contractor to replace the timbers and replace points south of Furnace Sidings.  In particular:

(a)   the deviation turnout

(b)   the facing crossover (down main to up loop)

(c)   turnout to Down Exchange Sidings and related diamond crossing

(d)   loop turnout south

This was a slightly more ambitious programme than first planned since the facing crossover was to have been removed.  The usefulness of the Down Exchange Sidings, which were brought into use in May 2008 for the purpose of stabling stock, had become clear however, so that, after due consideration of the cost,  the facing crossover was retained.

 

You would have though that it would now be possible for the long-suffering Permanent Way crew to rest on their laurels (or their shovels).  There were still plenty of outstanding jobs to do however:

(a)   removal of some largish tree roots from the trackbed by machine which were too large to move by means of pick, shovel, crowbar and profane language

(b)   clearance of ditches (including work associated with clearing November’s landslip

(c)   installation of bufferstops and a sand drag south of Blaenavon (High Level) station

(d)   installation of a properly engineered foot crossing near Forgeside, now called ‘Glantorfaen Crossing’

(e)   installation of a properly engineered foot crossing immediately south of Blaenavon (High Level) station

(f)   installation of facing point locks on all the points noted above:

 

 

With the first load of ballast laid into the platform by our volunteers the previous weekend, at last, after weeks of now, contractors KG Price start on the work of sawing off rail ends, and pulling up the rail.  Heavyweight tools are used for this work, which gains time at the cost of initial capital outlay – fine if you are at it five days a week, but pointless for weekend volunteers.  Even the use of a Telehandler is justified (the green thing seen poking in from the left) to carry the power tools to job.  Here the team rest briefly from their labours and smile (well, almost) for the camera.

0812 – 26 Jan 10

A few days latter, with the work extended half way to the foot crossing at Forgeside, rail appears with brightly shining ends, showing that grinding has been in progress.  Below the nearest fishplate, swarf is evidence that new rail ends have been drilled to accept the fishplates, whilst the ‘jump up’ on the nearest line of rails show how little wear there is the the ‘new’ rail when compared with our original rail.  Special joggled fishplates have since been fitted to smooth out the difference.

 

0834 – 29 Jan 10

 

 With the contractors drilling machine as evidence that the foot crossing at Forgside had been reached, we note that the crossing is no more than a hole in the face and a  track across the rails and up the muddy – and very slippery – bank beyond

 

 

 

 

 

0835 – 29 Jan 10

Turning to look south at the top of the broad bank is evidence of regular pedestrian traffic.  Despite local lore, it is not a Public Right of Way, but a private footpath established by the railway from its very early days, in order for the population of Forgeside to gain easy access to the station – just visible in the distance.  This was long, long before the arrival of any form of motorised traffic   PBRCo were determined to retain this pathway, both on historical grounds and as a service to the local community who have supported us so loyally, even though stringent modern safety legislation would demand the erection of a fence on both sides of the path.

0839 – 29 Jan 10

 

Chairman Robin marches smartly away from the centre of the work, as ballast is seen to stretch further down the platform.  Although there is more to do, the ballasting in the ‘four foot’ looks decidedly neat.  The gang in the background are taking a breather from tracklaying as they start the job of recovering old sleepers and arisings from the platform and station building work. In the distance the Coity is still wreathed in snow

0857 – 31 Jan 10

The gang with the works train. Ol’ faithful ‘Llanwern’ is sandwiched between the Lomac (carrying the dumper), then the Shark, two Dogfish and a pair of Grampuses.  In the background on the platform lie stacks of recovered imperial yellow bricks which are due to travel up to Furnace Sidings yard, though some will be retained for use at the station where the chimney awaits construction

 

0860 – 31 Jan 10

 

Two photos by our prolific Arthur Llewellyn.  Here at the loading point, just north of Furnace Sidingsstation lie two full Dogfish.  Beyond that the Lowmac, Warflat (painted a disgusting blue! )and a standard chassis carry sixty foot lengths of rail.  Each is 30ft, 40ft and 17.6ft long respectively - a novel way of carrying long lengths of rails!  The train, with a loco at each end, is due off down the line towards Blaenavon (High Level).  Even more novel is the technique for unloading the rail, and which  involves two locos and a short length of rail , 

Arthur Llewellyn – P1110725

‘Shark’ is a BR code name for ballast plough – and here it is seen doing exactly as it says.  This wagon was purchased at considerable cost, but was in excellent condition, and has proved absolutely indispensable, and money well spent..  It will soon be turning its skills to ploughing on the Big Pit branch, and, when not in use for yet further development, is likely to be seen bringing passengers round from Big Pit in bad weather – what a novel way to travel!

Arthur Llewellyn – P1110743

 

Comparison of dates will show that virtually all of February was lost to bad weather – these latest shots being the last day of February.   However here the four-foot and cess have been ballasted over the entire length of the platform and the area to the left has been cleared ready for the day when platform 2 is rebuilt and rails laid.  Despite an extensive thaw, flecks of snow still appear in hollow on the Coity

0938 -  28 Feb 10

Beyond the north end of the platform volunteer Wayne rest briefly on his shovel, whilst his son Dave fills one of the Grampuses to its limit.  The fine spoil is being tipped behind Furnace Sidings platform 1 in order to accommodate the width of the planned building there.  On the left Volunteer Charles is carefully sculpting the bank, now the gallant minidigger has done the rough work.

0944 -  28 Feb 10

 

Altogether some 2000 tons of new ballast from nearby Machen quarry were used on the extension (and some limited ‘topping-up’ on the existing passenger line).  Here PBR volunteers ‘borrow’ KG Price’s Telehandler for loading Dogfish.

0979 – 6 Mar 10

Here 48tons loaded and another 24 to go before 72 tons of ballast  roll off down to discharge their contents along the route.

 

0980 – 6 Mar 10

 

Foot crossing at Forgeside (uploaded 18 May 10)

As an aside from the relentless ballasting work, it was necessary to build a decent foot crossing at Forgeside.  For no obviously apparent reason it has been renamed after one the adjacent terraces Upper Glantorfaen Terrace, as Glantorfaen Crossing.  Glantorfaen means ’bank of theTorfaen’ an archaic name for the Avon Llwyd which appears and disappears in to large culverts at the bottom of the valley below.

 

An energetic crew make a start.  Ironically rails had to be lifted to instal six wooden sleepers, which had previously been concrete – the only location on the extension where this was found necessary.

0981 – 7 Mar 10

Still energetic, five give orders, one drilling ‘planks’ ready for bolting to the wooden sleepers underneath.  To the left of the telegraph pole the 4 ˝ mile marker indicates the distance from Brynmawr Junction – and a quarter of a mile to BHL

0984 – 7 Mar 10

 

A week later and with some tidying up, and a bit of ballast brings the sight of the crossing into contrast.  Dogfish and Sharks are all very well, but the final touches are still undertaken by the one manpower shovel!

 

 

0991 – 14 Mar 10

 

Viewed looking north towards Forgeside road over rail bridge, it is clear that laying the crossing has not been the only task.  Drainage had been seriously compromised by the laying of the cycletrack on the up side – a matter of questionable legality, from legislation enacted in 1845!  Once the ditch was dug the ash sub-ballast quickly drained and water flowed sweetly in the channel.  An offshoot off this work was the need to build a culvert under the crossing, the stone arch of which looks surprisingly as if ‘it grew there’.  On the left, like a hideous triffid, lie the mortal remains of a large tree-stump that had insinuated itself between the sleepers

 

0999 14 Mar 10

 

Father and son now demonstrate that the two manpower broom also has its place in PWay work, as a final tidy up after digging, prepares the track for ballasting

1019  –18 Mar 10

Looking down from Forgeside bridge southwards to BL we see Wayne and Dave sweeping the last part of the  last substantive length of track made ready for ballasting

1020 – 18 Mar 10

 

The distance to the end of the line gets about sixty foot shorter as another pair of rails are removed in readiness for the fitting of a buffer stop and sand drag.  In the foreground , proper planks are cut in readiness for the fitting of the foot crossing.

1014 – 14 Mar 10

At the other end of the line, dust shrouds the Dogfish- and volunteer Ian – as the Telehandler drops another sizeable bucket into the hopper.  This technique is very much faster than using our JCB with its limited reach and smaller bucket

1016 – 14 Mar 10

 

Point Timbering (uploaded 18 May 10)

The second major contract involving KG Price was the relaying and retimbering work for the ‘points’ (known in the trade as ‘switch & crossing (S&C) work.  Over the years timbers had rotted, cast fittings (‘the chairs’) had fractured, and things had crept out of alignment.  Under S&C rails are held to gauge by timbers rather than sleepers.  Where sleepers are wood – particularly in stations where appearance is important – they are made of softwood.  However S&C timbers are hardwood, and anything up to 25 feet long – so they are heavy – very heavy.  The use of hardwood is justified because we don’t want to re-lay and re-align any more S&C in our lifetime.  So the choice was clear, get in heavy men with heavy machinery – and they did the job in a fraction of the time we could have managed.

 

The first to be done was the lead from the main line into the yard.  Now it’s a legal requirement that where passenger trains ‘face’ into points (as opposed to ‘trail’, that all such points are fitted with Facing Point Locks (FPLs).  This view faces north so trains going south to Blaenavon (High Level) face into the points.  We had spent several years quietly fitting an FPL to these points and had only complete the works a few months earlier, when we had to take everything apart to enable the new timbers to be fitted.  Fortunately, it wasn’t too long before we got everything back together again.

1023 – 18 Mar 10

Now this is a rare bird – the facing crossover, much rarer then its close cousin the trailing crossover. The crossover consists of two points fitted back to back. The crossover joins two parallel tracks.  We had planned to remove this feature since it requires the expense and complexity of two FPLs, but its usefulness where is stands, and our desire to retain as much of the historic infrastructure as was possible demanded its retention.  As yet it awaits fitting of its FPLs.  Note thecontractors and their  complex apparatus for doing up fishplate bolts – PBR uses much simpler kit but it’s much slower.

1024 – 18 Mar 10

 

The up side of the crossover – not the finished product!  Here the timbers are being inched into their final position.  Next the rails and chairs will be inched into place, holes drilled and the chairs screwed down.

1027 - 18 Mar 10

Not pretty, but pretty effective. Contractors from KG Price get close and dirty to the trackwork

 

1036 -  19 Mar 10

 

Here are the point, partly reconsructed leading across a diamond crossing into the Down Exchange Sidings which are used to store trains.  For the moment only the diverging route us in use, the ahead route will be commissioned as Big Pit branch is re-constructed and this is a different project.  Since passengers will not be travelling over this route for a year or two, no FPL is fitted.

1074 – 28 Mar 10

The S&C in this area is quite complex, and included a so-called diamond crossing.  Over the last century or more  successive modification has resulted in a very poor alignment, and it was considered easiest with the effort now available to lift everything and start again.  Volunteer Charles looks down pensively and wonders if it will ever be possible to put the bits back together  

1078 – 28 Mar 10

 

It looks just as horrifying in the opposite direction….

1079 – 28 Mar 10

…but a week later things look re-assuringly normal.  The main line is functional again and  a few chairs need changing on the route to the Up Exchange Sidings.

1093 – 4 April 10

 

 

 

Page 1

 

Page 2

 

Page 3

 

Page 4

 

Page 5

 

Page 6

 

Page 7

 

Main development page

 

HOME