DEVELOPMENT – TRACKWORK (STEP 1.2.1) – Page 5

 

Page 1

 

Page 2

 

Page 3

 

Page 4

 

Page 5

 

Main development page

 

HOME

 

 

 

Trackwork through Blaenavon (High Level) station – and the end of the line (uploaded 21 November 2009)

Since our last upload on 14 October, the wood-for-wood sleeper replacement program has been completed through the station, as have the last two panels south of the station.  These will support a sand-drag (used, in emergencies to stop over-running trains) and, beyond that an earth bank or some bufferstops.  These will mark the end of the line for several years, until further southward extension (the so-called Phases 2 and 3) can be funded.  This may be many years away, and indeed the railway must demonstrate its financial viability before these important phases can even be contemplated.  To see details of the phases, return to ‘Main development plan’ and click on the ’The overall plan’.

 

This photo-survey, probably overdetailed, nevertheless marks an important milestone in the extension work – the completion of the sleeper replacement programme.  A little over a year ago, there were fainthearts who said it couldn’t be done in time, and to think of doing the bulk in concrete was complete lunacy.  It was the chance purchase of a second-hand minidigger that was the turning point.  However, the faithful little machine pictured here has borne the brunt of the work, and has never failed once in service.  The last month has, however, been marked by never-ending periods of wet and windy weather, and those few fine spells that do appear, perversely always occur during the week, when volunteers are generally out making a living.  As if that were not enough there was a requirement to lift the rails and sleepers on Bridge 19 (Varteg Road bridge) – a few yards south of the platform, and this took a day out of a busy schedule.

 

The PWay team has now reached the end of the line – but it is by no means the end of the story.  In the following weeks and months, the team must undertake jobs further up the line – replace rusting chairs under Bridge 18 (Forgeside Road) bridge, where water leaking from the deck above has cause severe corrosion, install facing point locks and fittings, pour many tons of ballast, pack and line the track, saw of burnt rail ends, drill them, and move the rails up to fill the gap sawn off, replace timbers under the points, and continue clearing ditches.  There’s no shortage of things to do – and then they have to start all over again on the Big Pit branch.

 

The second panel in the station is cleared ready for the rotten wooden sleepers to be replaced.  Despite assistance from the minidigger, the fine work must necessarily be undertaken by pick and shovel.  Here the team rest briefly from their labours and smile (well, almost) for the camera.

 

 

 

388 – 18 Oct 09

Looking generally northwards (ie up the line, the minidigger is seen at work, whilst volunteer Charles starts exploratory digging on Platform 2.  This platform is not properly really funded at this stage, but our undoubted expertise in building platforms on the cheap, and the opportunity to ‘get on with it’ are powerful incentives.  On the right the steel beams which are to support the canopy are roughly positioned.  The containers on the new works train are rather high, but just clear the beams – but not with the doors open – as we have already found out!)

0413 – 18 Oct 09

 

During a day of heavy and prolonged showers the sun did briefly pop out.  Sleepers are exchanged on a one for one basis so that the pitch is maintained.

 

 

0445 – 26 Oct 09

You could be forgiven for thinking that all PWay volunteers are built like the proverbial brick-built outhouse, but even placing the keys alongside the track (and on top of the platform in this case) by volunteers more slightly built makes a valuable contribution and saves considerable time

0446 – 26 Oct 09

 

It really is worth going back to page 1 and comparing this image with the corresponding image close to the bottom of the page.  The transformation is amazing, but, perhaps more significantly, the team that started had little experience, but have learnt their trade and honed there skills in a remarkable fashion.

0447 – 26 Oct 09

The very end of the line – at least, for the next few years.  The  last bed is cleared of soil and vegetation in readiness for the sleepers to be changed.  In the distance can be seen one of the parapets of Bridge 19 (Varteg Road) bridge.

 

0448 – 26 Oct 09

 

The foot crossing is very temporarily replaced, in readiness for the following weekend when the sleepers will be changed.  In this area some of the sleepers were so rotten they had simply disappeared!

0449 – 26 Oct 09

Looking the other way, nice new track awaits its new ballast.  It is worth looking at image 0021 dated 2 August to see just how dramatically the view has changed.,

 

0450 – 26 Oct 09

 

Local circumstances arising as a result of the work on Bridge 19 meant that the last panel was re-sleepered before the penultimate panel – which meant that the last panel was not really the last panel – if you see what I mean!  Here the last rail is just about ready to be dropped into its chairs on the new sleepers.

0584 – 15 Nov 09

And then, suddenly, it was all over – all the sleepers had been laid.

 

 

 

0587 – 15 Nov 09

 

The last fishplate is bolted into position…

 

0588 – 15 Nov 09

…and here is the job – finished at last.  The New Works team still have plenty to do on the building which has been significantly delayed by the poor weather.

0589 – 15 Nov 09

 

 

‘The PWay train homeward makes its weary way, and leaves the world to silence and to me’.  The poet Gray’s ‘Elegy written in a country churchyard’ seems perfectly in tune with the moment as the PWay train, and the PWay team, their work finished here for a few weeks, trundle off back to the yard

0596 – 15 Nov 09

 

 

 

Page 1

 

Page 2

 

Page 3

 

Page 4

 

Page 5

 

Main development page

 

HOME