DEVELOPMENT – BUILDING AT BLAENAVON HIGH LEVEL STATION (Step 1.4.1) – Page 2

 

Page 1

 

Page 2

 

Page 3

 

Main development page

 

HOME

 

Progress at Blaenavon (High Level) Station Building  (uploaded 23 November 2009)

Our last upload on this topic was exactly two months ago.  In the interim, work has continued without a break on the station building at BHL.  It has been a difficult two months.  The days a getting shorther, and there has been increasingly poor weather, as many in the UK can testify.  Strict financial controls have recently been a problem, though that has now, and technical problems have resulted in many a furrowed brow.  More recently the decision on whether to use wooden or steel beams to carry the buildings canopy has caused much discussion.  In the end, steel beams were chosen, but ordering them and the drilling and cutting them ready for installation was time-consuming.  There are seven beams in total (as there were in the original station building).  The beams, which are about 6.8m (22ft 3ins) long and extend about 2.5m (8ft 3ins) beyond the building, weigh 156kg (342lbs) each.  As laid, the front wall supports about 80% of the weight of each beam, with the back wall supporting the remainder.  However when the weight of the canopy structure is added, the beam will tend to tilt about the front wall, so that the weight borne by the rear wall may even be negative.  This demands special fixing methods to ensure stability.  The dynamic loading on the beams during windy weather will place heavy demands on the structure and special measures will be employed to allow the canopy surface to lift if conditions become too bad.  Ordering the beams, cutting and profiling them to shape, and drilling all the necessary mounting holes took several weekends, and additional time was spent designing and building the straps which would fix them to the block structure.  All in all, the beams became a project in themselves.

 

During recent weeks when the wind howled and the rain lashed, washing newly laid cement directly from the block work, there were days when it appeared that nothing had been done – and it was sometimes it was felt that we had even gone backwards, but viewed over a period of two months the progress has been substantial.  The images below show just how much progress has been made. 

 

 

September was generally a good month, and this image shows that the fireplace, recovered from the shop (see News, page 3) fitted the embryonic chimney just perfectly.

0354 – 26 Sep 09

Here the minidigger is busy in loading the first few of the seven canopy support beams (described in the text), into place, limited lift height and the front wall meant that there was very limited clearance

0389 – 18 Oct 09

The minidigger needed to be at full height and full stretch to drop the beams into place, and this view shows just how little room is available at this point

 

0390 – 18 Oct 09

 

The beams had been transported from Furnace Sidings, where the preparatory work had been undertaken, in one of the two Grampus wagons.  Here is the minidigger lifting one of the beams.

 

 

0392 – 18 Oct 09

We knew that the clearances were going to be tight and that slinging would be a problem, but once we got the hang of things, and tehered each end, it progress was smooth and event-free.  Volunteer Ian leads the beam by its tether whilst the digger crawls down the platform

0396 – 18 Oct 09

Here volunteer Wayne releases the beam from the digger bucket.  The limited clearance meant the use of some rather novel means of slinging.

 

 

 

0397 – 18 Oct 09

 

Six of the seven beams are roughly – very roughly - in position as Wayne gesticulates his requirements to volunteer Gareth.  Gareth smiles laconically from the window – and completely ignores them.

 

 

0401 – 18 Oct 09

The nerve wracking job of getting the beams up is complete, and they lie higgledy-piggledy on the building walls.  Underneath the New Works team is joined by a few bodies from the PWay team who have helped during the operation, as they enjoy a cuppa.  This was the last decent day of the year

0406 – 18 Oct 09

The job of getting the beams the right way up, in their correct attitude and in their correct position was a job best done by one or two people in relative peace and quiet and without rush.  Here are the beams in position and in a straight line – but problems remained.

0468 – 26 Oct 09

 

Along the front wall, the enveloping process is almost complete, with blocks only required in the most southerly two bays.  This was a busy day, with the PWay team working outside, their Shark is seen through the double doors.

 

0595 – 15 Oct 09

Onlookers sing Pink Floyd’s ‘Another brick in the wall’ as volunteer Wayne, at absolutely full stretch, and in steady rain and a whole gale, drops the final block in the back wall.  The beams are now sealed in place.  Plastic membrane allows for thermal expansion through the front wall. No such luxury is afforded at the back.

0605 – 22 Nov 09

Despite getting the beams in the correct position (see image 0468), several iterations and much time were needed in finally driving out cumulative errors which made the distance between the sixth and seventh beams incorrect.

 

0606 – 22 Nov 09

 

The back wall is seen completed.  Even with the appalling weather on the day, for the first time, with a little imagination, it’s possible to envisage a snug station building.

 

 

 

0607 – 22 Nov 09

Compared with image 0595, we see the last two bays of  blocks completed.  The Way team went the previous weekend, hence the view through the double-doors. The fixing of the straps to the beams employs a sliding arrangement which permits free thermal longitudinal expansion of the main beam, whilst constraining it laterally and vertically

0608 – 22 Nov 09

Few images have been taken of the south wall, but her it is essentially complete. The first block of the final course is in place.  Beyond this the ‘pine end’ will be built in light-weight Thermalite blocks, but construction of this latter part will wait till the roof trusses are up.

 

 

0609 – 22 Nov 09

 

 

Page 1

 

Page 2

 

Page 3

 

Main development page

 

HOME