DEVELOPMENT – FURNACE SIDINGS PLATFORM TWO (STEP 1.3.1) – PAGE 2

Furnace Sidings Platform 2 – Page 2 (added 23 October 2008)

With the brick front leaf approaching completion, it was time to start on the slabs that formed the platform’s upper surface...

The first two shutters look clean and shiny before the first pour – they weren’t to stay that way for long

1216, 1217, 1218 15 May..

The design is complicated by the need to support a 12 inch overhang over the platform wall

Following a successful pour of mass concrete for the  bridge foundation on platform 1, preparations are made for the second foundation

 

Andy Knock, Ian Longworth and Wayne Evans pour the first of the 26 slabs, in positions 4 and 6

1229, 1230  17 May

 

First two shutters just poured and trowelled, in positions 4 and 6 (the first three slabs are on the ramp which is deferred till later).

 

 

The residue from the first pour is poured into the mass concrete base for tower 2 of the footbridge.

1222,23,24 17 May

 

But horrors! it was almost a ton short and the balance had to be mixed and poured very quickly

Phew!  Andy and Wayne relax ready to trowel off the top surface of the base

 

View north, on 31 May, as the brick wall approaches completion.  The first two slabs approach full curing strength and are due to have their shuttering struck down.

1398,1399 31 May

Whilst looking south it is clear that one good weekend will see the brick wall finished

 

Eric Edwards, brick benefactor to the tune of 2700 new bricks, lays the 3902th and last brick in the wall.

Immediately followed by Ian Longworth attending to the final tittivation

 

 

 

With the wall now complete, it was possible to march down the platform with the ‘outside’ shutters. The six images above attempt to show the sequence.  For economy and manageability, the general method was to build five shutters and to move these down the platform as each slab was cured.  The  scheme was that once the ‘outer’ slabs were complete, the ‘inside’ – and rather simpler – shutters were constructed from the now redundant ‘outer’ shutters, and the ‘infill’ slabs completed.

Pict 1489,90,91,92,93,94 No date

 

The Diesel Gala on 25 and 26 July met with warm sunny weather.  Each of the industrials lined up on platform 2 appears to have a small platform to itself

1724, 1723  25 July

At the northern end, the second pour has already joined sections 4 and 6  to give a 10m ‘mini-platform’ consisting of sections 4,5,6 and 7

 

Flaming August!  Many, but not quite all, the members involved in the construction, immediately upon the completion of pour 4 on 16 August (left to right).

Back row: Andy Knock, Norman Clymer, Charles James, Alastair Warrington, George Pope, Wayne Evans, Peter Drummond, John Down

Front row: Arthur Llewellyn, Mick Parker, Dave Perham, Gary Pearce, Rhys Davies, and Ian Longworth

Others in the Roll of Honour  include Eric Edwards, Ian Smith, Alex Drummond, the remainder of the Evanses,(Frieda, Matthew, and David) – and not forgetting Colin and Mary Boor who kept the team going with gallons of tea, toast, toasted tea cakes and even the odd choccy biccy – Ooh! There’s sinful now, look you!

1768 16 Aug

 

On 16 August, a narrow window in the incessant rain allows pour 4 to be made, and within an hour, its raining yet again

1769,1770, 16 Aug,  1778  22 Aug

In an image, perked up to make it look a bit brighter, we see the shuttering supports.  The effect of the downpour was to give the panels a finish reminiscent of Terazzo marble.

On the rare dry evening of 22 August, the final tweaks have been made to the membrane and re-inforcing ready for the following day’s final pour.  The sun sets and fingers are crossed for the dry weather to continue

 

The sun has set behind the Coity, and the trees at Ty Rheinallt Farm stand silhouetted against the sky.  Will the weather hold?

 

 1780 22 Aug, 1781, 1782 23 Aug

A smaller team than last week wait for the concrete lorry, a little before 8.00am on a clear Saturday morning.  In the foreground is Wayne Evans, then Dave Perham, Peter Drummond, Charles James, Norman Clymer and Rhys Davies give a good impression of farm labourers

The deed has been done, with just a bit of final trowelling and tweaking to be done – but look at that blue sky.  True to form , it did not last long.

 

The evening of Tuesday 26 August - time for the coup de grace – the final shuttering strikedown.

1793,1798,1800  26 Aug

The Shutters are down and the results are near perfect – pity it took us five attempts to perfect the technique!

A few minutes later Arthur Llewellyn had disappeared with the shuttering, and the platform can be viewed in its unadorned entirety

 

From the south, though we say so ourselves, the results are impressive

1801, 1803 26 Aug

...and no less so from the northern end, as yet another damp evening envelops the valleys

 

Click HERE to return to Page 1

 

Click HERE to return to main Development page