DEVELOPMENT – BRIDGE 14 (Step 1.2.4.2)
Bridge
14 (uploaded 14 November 2008)
Bridge 14 is loosely referred to as the ‘New Pit Road bridge’. It is a long bridge, 59ft 3ins between its
abutments, but is mercifully square – not skewed like Bridge 13. Visitors to Big Pit pass through it on their
journey from town. Amongst all the bridges
in the area, it is probably the best maintained, and therefore requires fairly
minimal work to bring it up to scratch.
Funds for this work are in place, and work is expected to begin early in
2009.

|
A clean,
straightforward girder bridge, but with an attractive curved top to the longitudinals
– and long enough to rumble loudly when trains pass over it. This is the view the visitor to Big Pit
will see. He will need to turn right
just by the big winding gear wheel.
Carrying straight on and curving left will bring him to Doncaster’s works. Initially in the
business of making tyres for railway engines carriages and wagons, they now
make turbine blades for RB211 jet engines! Doncaster’s are currently involved in a major expansion of the works.
|
This is a view
of the bridge looking roughly east.
Visitors to Big Pit cannot be over-impressed by having to travel
through an industrial estate before reaching their destination
|
.....
|
Above the bridge
looking north we see Bridge 12, the notorious ‘Rail-over-Rail’ bridge in the
distance. Virtually invisible between
the photographer and Bridge 12 is Bridge 13.
On the right can be seen the water tower in the middle of Furnace
Sidings yard. The track in the
foreground was re-sleepered in mid-2008.
|
The bridge
deck,and the line on it is steeply
curved and canted and also on a steep downhill gradient. The Railway Inspector was concerned with
this, but we appeased him by offering to introducing a permanent 5mph speed
limit on down trains. The massive pile
on the right is not a slag heap, but earth arising from the works involved in
Doncaster’s expansion activities
|
Progress!
(uploaded 18 April 2009)
Of the bridges along the line Bridge 14 was in the
best condition, work was confined to patching a few small holes, welding and
bolting some small holes in the main longitudinals, replacing the longitudinal
baulk timbers, and painting all newly exposed metalwork – especially the
‘orrible galvanised handrails, installed a few years ago.

Bridges
along the route needed more or less scaffolding on them, and Bridge 14 was
troublesome since, despite needing least work, it crossed a busy road going
to Big Pit and Doncaster’s works. In
order to manage the traffic, it was necessary to widen the road, albeit
temporarily. Here, on 13 January
2009, a strip has
been strip dug out to permit widening.
1838 13/1
|

The
hole which had been dug had to have a strong sub-base, not only to support
the weight of vehicular traffic, but to safeguard a gas main which was only
an inch or so below the surface. Here
is the situation looking west (towards Doncaster’s and Big Pit) a few days later on 17 January
1846
17/1
|

By
the 22nd Griffiths of Abergavenny, the main civil contractors, had
made a rapid start by removing all the cess walkway decking, though at this
stage the ‘four-foot’ decking remained outstanding. This view is looking up the line towards
Bridge 13,12 and Furnace Sidings.
1864
22/1
|

By Sunday 25 January the rails chairs and fittings
had been removed by PBR
1877 25/1
|

A few days later the’four-foot’ decking and main baulks
had been removed leaving the bridge a trap to the unwary
1915 1/2
|

The situation was even more startling
when viewed from below
1916 1/2
|

Mid-February
saw the second round of snow, and this miserable scene sees the one way flow road
traffic management arrangements in place.
Part of the work was to fit substantial steel stiffeners at the ends
of the longitudinal beams, and this was an important reason for the
scaffolding
1979
14/2
|

…but by mid-March Blaenavon was bathed in bright,
warm but slightly hazy sunshine.
Looking north the new baulks are in place. Note the kinked joint required to
accommodate the curve
2119 19/3
|

A view in the opposite direction. The
baulks are about 2.5 inches wider than their predecessors in order to allow
‘check rail chairs’ to be fitted. This
will permit the installation of check rails which will avoid the imposition
of a severe speed limit over the bridge by HMRI
2125
19/3
|

Left: In April, three workers (the third largely hidden
behind the second) enjoy the sunshine as they notch transoms and fix the
steel straps that hold the baulks in place
2183 3/04
|
The scaffolding is moved to the south end of
the bridge. This will allow the south
end stiffening ribs to be welded into place- as well as painting a few
previously hidden places
2220 6/04
|
|
Modifications!
(uploaded 18 May 2010)
Bridge 18 is crossed by track on ½ mile radius. This
is quite sharp by railway standards, and demands that the track has a pronounced
cant or ‘superelevation’. We were always
aware that the cant was pronounced, but having been visited by two inspectors,
neither of whom had mentioned it, we were happy that the bridge was rebuilt as
it was – after all it had carried heavy coal trains up till 1980. We were a little surprised when the second
inspector during a visit in April 2010, whilst
generally happy with what we had done to date, demanded that the cant be
reduced. The only way that this could be
done was to contruct complex packing pieces, tapered in two planes, and, like
the new baulks, fabricated in hardwood.

The work, which took about three days, was
completed on 2 May. The tools of the
trade are evident, to whit, one Duff-Norton jack, two crow bars - and three
cups of tea!
1208-2 May 10
|

The final chair screws go in! In the foreground can be seen the original
baulk timber and the packing pieces in a paler shade of wood. The fringing effect on the side of the
building is a result of reducing the image resolution for web use, and is not
real
1212 - 2 May 10
|
Click
HERE to return to main Development page
