Bridge
13 (uploaded
This is Bridge 13, a slender, highly skewed bridge
with a span of 40ft square on, but
nearly 52ft on the skew, and which has become the most difficult structure to
restore for regular traffic use. A
concrete road passing underneath it once provided access for miners to Big Pit,
and is thus referred to locally as the ‘
The bridge is in poor condition with significant
corrosion in the joints between the two large longitudinals
and the transverse beams underneath. The
bearing pads at each end are also breaking up.
We were not prepared to accept replacement of this historically
interesting bridge with a modern version – probably of re-inforced
concrete, and fought for its retention.
Although we seem to have won this battle, the cost has been that the
bridge deck must be supported by a pair of massive four-feet deep girders
underneath. Not pretty, but it won’t be
seen by our passengers, and hopefully the bridge will continue to rumble
impressively when trains pass over it.

Viewed from the nearby cyclepath, this is a view, looking broadly west, under
Bridge 13 Viewed from the
other side, looking east
Physical work on this bridge is expected to begin
early in 2009
Main
beams installed (uploaded
.After over a month of work the final big step on
the difficult Bridge 13, and indeed, the final big step on all of the bridges
(17,16,14 and 13) in the project to extend the railway
to Blaenavon (High Level) finally took place on Thursday 9 April, when the new
four-feet deep re-inforcing beams were hoisted into
position. Although we will upload a more
detailed history in due course, we thought you’d like to see a few images of
this important event. With this work
done, the route to completion is now clear, and clearly not far off. We have been given a date of 23 May, but it
may be even quicker than this.
|
The
original bowstring longitudinals, and their cross
girders (painted in grey primer) are
retained, but serve little purpose other than to retain a heritage
appearance. Rails and trains are
supported by the massive 4ft deep beams seen under the original bridge. Img_2257rr |
The new
beams support a number of cross girders (or rather, outriggers, since they do
not touch the outer , original, longitudinals). Here we see one of the many cross girders
being lifted onto the new beams. The
grey cleats on the new beam , in turn, support the massive wooden beams to
which the chairs and rails are attached.
The wooden beams are up on the embankment standing by ready to be
fitted. Img_2258rr |
Click
HERE to return to main Development page