DEVELOPMENT – BRIDGE 12 (Step 1.2.6.1 and 1.2.6.2)

Bridge 12 (uploaded 26 April 2009)

 

Bridge 12 is the rail-over-rail bridge, and, unless anyone tells us differently, we believe it to be the only standard gauge rail-over-rail bridge in preservation.  That is to say, both ‘under’ and ‘over’ routes are in preservation.  There is of course the famous bridge on the Dduallt spiral on the Ffestiniog, but this is narrow gauge, and in any case, is a post-preservation artefact.  There was also the Swansea Vale Railway which had a bridge under the main line near Pentrechwith but, sadly, this railway has closed.  So, so far as we are concerned the rail-over-rail bridge is something special.

 

Not only is the bridge probably unique, but it has been difficult to manage its restoration.  Indeed there were faint-hearts on the railway who said we should demolish it, but bulls have been grabbed by the horns, funds have been found and the bridge has undoubtedly returning from dereliction.  Bridge 12 has an important role to play in both the extension to Blaenavon (High Level), (Step 1.2) – trains must run under it to reach Blaenavon, and in the Big Pit branch project (Step 1.5) where it will provide a route for the branch trains back to the yard and a footpath/viewing platform for visitors who want to see trains on our ‘main line’.

 

The limited range of funds available for the extension work meant that initial work on the bridge would be confined to making the bridge safe only for trains to pass under it.  However, now that funds for the Big Pit branch have been secured, work has finally started on repairing the wing walls and reconstructing the main deck so that trains can pass over it.

 

This bridge is somewhat different from the other bridges and the repair work was awarded to a different contractor.  The contract was let on 21 January 2009 to Cambrian Transport of Gloucester.  In like manner to the previous bridges, PBR would be responsible for lifting and storing the track, and the images below, uploaded shortly before the bridge was completed attempts to tell the story.  A few photos of the work to prepare the bridge for passage of trains under (Step 1.2.6.1), appear in our News Archive, a few paragraphs down from HERE since, strictly speaking, this page describes only the work of Step 1.2.6.2

 

Images and captions (uploaded 22 June 2009)

.. .. 

Early February brings inhospitable conditions.  The bridge in seen in the centre of the picture.  The 3 ¾ mile milepost appears directly under the arch. 

 

 

 

1984 14 Feb 09

The contract called for PBR to lift the rails and sleepers on the bridge.  This was small beer to our intrepid PWay team, who had done the job a few days earlier.  The situation was made complicated since a set of points lay on top of the bridge and it was important that the sleepers, fittings and rails were all marked so that they  would go back precisely in their original positions

1988 14 Feb 09

 

Looking north into the yard it is easy to see the rails diverging from the position of the points.  The points are on the south side of the bridge, the northern half once also carried a line of rails, but is currently unused

1992 14 Feb 09

Looking back the other way, in the general direction of Big Pit, it is possible to see that the bridge, in comparison with those on the main line, is very wide, and unlike those single line bridges is supported by three rather than two longitudinal girders

1995 14 Feb 09

 

A thaw brings better conditions, but there is still substantial snow on the distant Blorenge mountain.  This shot was taken a little further back than the image above it.  The crossing  in the foreground once led to the second line of rails across the bridge.  There are no plans to re-instate it

2009 17Feb 09

Once the contractors has scraped off the ballast it soon became clear that there had been widespread failure of the bitumen waterproofing, and as a result a large fraction of the timbers had rotted beyond redemption, and would need replacing.

 

2105 9 Mar 09

 

Meanwhile the abutments, especially on the Furnace Sidings side of the bridge needed extensive re-setting and pointing.  The deck under the bridge was intended  to provide a stable platform for subsequent scaffolding, additionally, the fast-running stream that flows under the bridge had to be protected from any lead-based paint chippings or dust which might contaminate the water supply.  The scaffold tower provides access to the abutment and wing walls on the north west side

2144 24 Mar 09

A week later the scaffolding which supported the crash deck underneath the main span was up, ready for initial work on the steelwork.  The triangular section of the wing wall in the centre of the picture had been largely re-pointed, but the area in the upper centre had bulged and had to be removed and re-set.  It may just be possible if your monitor has sufficient resolution to see the numbering on the stonework, to ensure things went back in their proper place!

2185 3 Apr 09

 

After the shock of the condition of the decking timbers, a second even more serious shock unfolded as the twenty or so steel cross members were seen to be in very much worse condition than an initial inspection had revealed.  At first only one cross members was earmarked for replacement.  As the true condition was realised, the number of girders to be removed increased, and here we see the second being cut from the overall assembly.

2219 6 Apr 09

Cambrian’s workers, on the left, continue work on the masonry.  More than mere re-pointing is this, as massive stones and large quantities of soil are moved around.  On the right Cambrian’s sub-contractors inspect the parlous state of the cross girders

 

 

 

2259 9 Apr 09

 

On the downside north wing wall the bulging masonry has been re-set and re-pointed.  It just remains for the heavy capstones to be re-set.

 

 

 

 

 

2367 28 Apr 09

The need to fit scaffolding on this bridge, the nearest to the yard at Furnace Sidings, effectively maroons everything south of it – including the other bridges and the station at Blaenavon (High Level).  Removal is planned before the weekend 27/28 June – a month after the blockade caused by the remaining bridges had been lifted.  On the left is the decking over the stream, whilst on the right, the milepost seen in the first image of this series is seen.  The sleepers were replaced by PBR just days before the bridge was handed over to Cambrian.  The gradient beyond the scaffolding has been measured as 1 in 24 – and on a steep curve to boot!

2376 28 Apr 09

 

Heavens – what’s going on here?  Amid ear splitting noise, and under supposedly dust proof sheeting the grit blasters get to work, cutting back the rust to reveal the true state of the steelwork

2382 1 May 09

A camera held at arms length and through a small hole in the ‘tent’ reveals the inferno inside.  The vague shadow on the left, with air hose at the back is human – we think.

2383 1 May 09

 

As the dust settled the full extent became clear, as can be seen in this view of the south east corner of the deck.  The cross girders on the ‘rail’ side (that is, the south side) of the bridge were essentially beyond redemption.  On the ‘path’ side (the north side), one or two girders would need replacement.  At this stage it was considered wise to ‘future-proof’ the bridge by replacing ALL the cross-girders despite the fact that such a move would increase costs.  This was more than just a matter of cutting out all the cross-girders and replacing them – there would be nothing to hold the side girders up – hence the need for the safety chain. 

2408 3 May 09

If that were not enough the middle longitudinal girder had both twisted and moved and it was necessary to jack it up and build new  pedestals upon which the middle girder could sit.  Problems were also found on the outside longitudinal girders, which were to be patched.  In the event the patches (one inside, one outside so that with the original plate, a sandwich was formed were made to the full dimensions of the original.  This was true ‘battleship engineering’ in the old style.  We cannot imagine this bridge failing in the next century.  In this view of the north west corner of the deck, most of the cross-girders had been replaced.

2472 30 May 09

 

In the south-west corner, all the old girders had been removed.  Apart from the safety chain, one of the two temporary cross girders are in place, with one of the new substantive cross-girders in the foreground.  Welding of steel is a well known science these days, but welding to wrought iron still demands specialised materials and welding techniques.

2799 9 June 09

The repair of this bridge has brought forward a number of unexpected challenges, each of which has in turn demanded changes in planning and approach.  In mid-June we’re on the final furlong the way forward now clear to see.  The steelwork needs painting, and the deck need renewing, but the end is in sight.  The smiles on the steelworker’s faces are testimony to the fact that the finish line is near.

2820 15 June 09

 

We anticipate only one further report on this bridge.  By the weekend of 27/28 June, the steelwork will be painted (this was, in fact, completed on 20 June), the wooden deck installed and the scaffolding under the bridge, which has hampered work on the track and at Blaenavon (High Level) station will be removed.  At this stage PBR will be able to lay the track on the bridges further down the line, complete its track renewal program and finally get to Blaenavon (High Level).  Back on Bridge 12, there will be outstanding masonry work to complete, as well as the sub-base to be laid on the new wooden deck, which in turn will allow PBR to relay the rails and points.

 

The final fling! (uploaded 28 September 2009)

After late June the bridge made steady progress to the final completion of the contract.  The important dates were 25 June when the crash deck and scaffolding was removed.  This step finally allowed trains south of the bridge, and it was only a few days late that our PWay team had re-laid the rails on Bridge 13, and were making progress on Bridge 14.  Progress to 25 June had, taken rather longer than expected (by about a month), but in the grand scheme of things, this delay was largely absorbed.  What we got was much more than intended, and by about 8 August the remaining physical work on the bridge, which was mainly confined to the deck was complete.  The requirement for comprehensive documentation, and inspection by third parties took a little longer, but by 24 August the contract was complete and the final payment made.  PBR’s PWay team still have to replace the points and track on the bridge, but, all in all, a very satisfactory outcome.  Following completion of gritblasting and installation of new beams, the steelwork was painted with specialist paints.  In the case of bridges, the primary purpose of painting is to maintain a waterproof layer and to prevent corrosion – also looked very smart too.

 

Following completion of gritblasting and installation of new beams, the steelwork was painted with specialist paints.  In the case of bridges, the primary purpose of painting is to maintain a waterproof protective layer and to prevent corrosion – but there’s no denying that the finished article looks attractive.  Here we see the northern half of the deck looking west to Big Pit.  Although there are no immediate or medium-term plans to run a track over this side of the bridge, it was considered wise to ‘futureproof’ the bridge by providing the potential to carry trains on two lines of rails if they are ever needed.

2840 23 Jun 09

With painting complete, the next task was to replace the wooden decking.  When the old deck was stripped it was clear that about half of the timbers could be re-used, but, once again, the decision was made to replace ALL the timbers ,for the same reasons as given alongside.  The original but serviceable timbers thus released will be used as point timbers around the yard.

 

 

 

2843 23 Jun 09

 

Viewed from the edge of the site of the Up Exchange Sidings (soon to be brought back into use in order to accommodate the Big Pit branch), a large mobile crane is seen, dropping the new timbers into place.  The scaffolding which supports the crash deck is still in place, but, with the deck in place, it will no longer be needed.

Although difficult to see in this scene, containing as it does a welter of different gradients, the bridge deck slopes down to the left at a gradient of 1 in 40, immediately reversing its slope to 1 in 40 up on the eastern abutment.  The gradient underneath is 1 in 24 over a short distance.

2851 23 Jun 09

Here is a close up of new and recovered steelwork. The original plan was to replace only one or two of the cross beams, but it soon became clear, following exploratory grit blasting that the most economical long-term route  was to replace them all.  As noted above, the two outside longitudinal beams were originally to be patched, but eventually it was quicker, easier and better to sandwich them.  Only the centre longitudinal beam escaped largely unscathed but best part of a week was spent jacking and packing it  into position and removing a long-standing twist.

 

2856 23 June 09

 

Installation of the deck timbers is completed. The centre beam is buried under the timbers,in this view,  looking south-west towards Big Pit.  Passengers on the Big Pit branch will join this route from the right, whilst the route over the bridge will only be used for shunting and for special workings The width of the bridge can appreciated in this view – the only double track bridge on the line.

 

2862 26 Jun 09

With the deck timbers in place, no time was lost in removing the crash deck and the scaffolding.  A few more hours were taken to remove the polythene sheet, ply and heavy sleepers that had been used to protect the leat which runs through the bridge from contamination by blasting grit, and, more seriously, from paint residue that might contain lead.  The impressive extent of the work re-setting and pointing the masonry abutment is clear

2863 25 Jun 09

 

 

Masons with the skills to work on the heavy stones that make up bridge abutments don’t grow on trees, and two of these three were drafted in from the deep West Country, all three were also involved in demonstrating  the variety of skills on the steel deck, and on the special bearers required to support the deck.

 2865 25 June 09

’Da management’ looking very happy that the job is all but complete.  There were some worrying moments, and there were a few times during the course of the work when brows looked decidedly furrowed!

 

2885 6 July 09

 

Between the decking timbers and the track a complex smorgasbord of materials protects the timbers from water damage.  The first layer is heavy black sheet of some type of rubber polymer, a semi-permeable white sheet sits on top of this.  Small piles of pea grit prevent everything blowing away.  The management of water on this sloping bridge was always difficult, and repairing and replacing the drainage system so that it would not fail for many years was complex.

3095 25 July 09

PBR had agreed to spread the ballast, so with all the contract staff, except one technical man drafted to ‘other duties’, we see technical input provided through the medium of the Mark 1 shovel, whilst over 30 tons of ballast are spread onto the eight tons of pea grit already laid. As the job moves to a successful conclusion the ‘technical man’ looks deservedly happy.

 

0038  6 Aug 09 

 

 

Postscript (uploaded 28 November 2010)

We had thought that we need not report further on Bridge 12, albeit aware that we had not reported on the relaying of the rails.  However a year and a month later the situation allowed this relatively small item of work to be completed by our own volunteers.

 

It is not planned that passenger trains travel over the line which includes the ‘rail over rail’ bridge but it is likely to form a quick route in and out of the yard for locomotives that are working the Big Pit service.  Here the sleepers (which had been stored on either side of the bridge and carefully numbere4d) are returned to their original positions.

7755 - 26 Sep 2010

A fortnight later we see the job approaching completion.  We were rather surprised having regard to the large pile of ballast on the right in the previous image, that we needed more, and this delayed completion as there were no convenient means of bringing the ballast to the work site

 

7771 – 10 Oct 2010

 

 

Click HERE to return to main Development page

 

 

First uploaded 26 April 2009

Images and captions uploaded 18 June 2009

Second section uploaded 28 September 2009