In overall plan terms Platform 2 at Blaenavon (High
Level) station (referred to henceforth as BHL) is quite a long way down the
development priority list. There is
unlikely to be an operational requirement for such a platform for several
years, furthermore there is no funding to support its construction. So why are we getting involved in it now?
Our gallant New Works team have built two platforms
in two years, and certainly can be viewed as experienced by any standards. The team are at BHL, and have been
effectively marooned, so that if work is prevented on Platform 1 for any
reason, their gaze naturally falls on Platform 2, and with their innate desire
to ‘get on with things’, Platform 2 became irresistible. As things stand, it will not be possible to
embark on construction of the platform at Big Pit for several months. The team
have also demonstrated that they can build platforms very economically, using
scrap material wherever possible. As an
example of their parsimony, new 2 x 4in timber was used to provide slab
shuttering for Platform 2 at Furnace Sidings.
It was then used to provide props for the platform overhang. It then went to BHL Platform 1, where it was
again used to provide shuttering. It was
then used to provide supports for the windows and door apertures during the
construction of the building walls.
Finally, those bits that were long enough were used to provide posts for
signs, and those pieces that were too
short were used to build trestles and horses.
Within the overall plan, it is exceedingly unlikely that, in physical
terms, there will be time to do more than make a start on Platform 2, before
the Big Pit platform calls, nevertheless it has forced a more detailed
examination of the plans, and a more critical ground survey has been made.
In physical terms platform 2 will be almost mirror
image of its partner. That is to say it
will have a flat top surface that is 267 feet long, with ramps at each end,
each about 21 feet long. The construction will essentially copy Platform 1,
that is, coping stones about 2 feet wide along the platform edge, with the bulk
of the platform surfaced in tarmac.
There will be no ‘planked’ portion as on Platform 1, as there was no
signal box, which required a route for its wires and rods under the
platform. On the north end of Platform 2
once stood a water tank supported on a masonry structure. There are also signs that there may have been
a water crane situated there. The extent
to which these can be reconstructed or reproduced is as yet unknown, and will
need some deft archaeology by the New Works team before we can judge how to proceed.
The cycleway runs very close and parallel to the
site of platform 2. There is a minimum
width specified for passenger platforms, and for a while we had thought that we
would have insufficient width to accommodate the platform without encroaching, albeit
slightly, onto the platform. Indeed,
preliminary discussions had already been opened with the local authority about
adjusting the fence line. This had the
potential to grow into a process needing protracted quasi-legal negotiations,
before the ground survey noted above revealed that there was not only
sufficient room, but several inches of slack.
Although the platform, as a mirror image of Platform 1, will be dead
level, and of the same height. the cycleway, against which Platform 2 will
essentially abut, slopes gently downwards towards the south, and is generally
lower than the platform. At the north
end the cycletrack is about six inches lower than the platform, about twelve
inches at the centre and about 20inches lower at the south end. Accordingly, there will be a low block wall
at the back of the platform, and the plan is to build a low edge nine inches
wide and about two or three inches high at the back of the platform (built from
yellow bricks recovered from the building) which will carry a typical LNWR
fence along its length, of identical pattern to that on Platform 1.
Unfortunately, as things stand, it is unlikely that there will be sufficient
space to build even a rudimentary shelter.
Although more images will be added in the next day
or so, the few below are added to ‘start things off’.
|
This is a
view, probably from around the mid-fifties, looking southwards with Platform
1 on the left – and of course, Platform 2 on the right. The first locomotive is one of the heavy
42xx 2-8-0T locos, and the one behind appears to be of the same class. These were the usual locos to work the empties
up, and coal down. However the main
reason for this picture is to show the water crane to the right of the
leading loco, for it is the drain associated with this crane that is featured
in the images below. In fact, to the
left of the loco in the rear it is JUST possible to see the water crane at
the south end of Platform 1, which once stood in the blue brick walled
structure to the south of the platform.
Getting a water crane back into operation at either of the sites of
their predecessors would be a real challenge. |
|
|
Left: Looking broadly south , the northern end
of the site of Platform 2 has an indentation in it. This was the site of the drain for the
water crane, the upright of which lay to its right. 0370 – 11 Oct 09 Right: Standing on the platform and looking in the
opposite direction the water crane would have been placed on the left. On the right are new sleepers, dropped
ready for laying in Platform 1 by the PWay crew, parts of which can be seen
on the upper right. 0371 – 11 Oct 09 |
|
Click
HERE to return to main Development page